Thursday, November 4, 2010

Soldier Piles

Steel piles are either driven or drilled in at intervals along a wall for the attachment of wood lagging or sheet steel to allow excavation to continue similar to a row of soldiers standing at attention.

Typical Steel Soldier Pile with Wood Lagging




Typical Soldier Pile Drilled into Rock




Typical Braced Soldier Pile




Typical Soldier Pile, Rock Bearing, with Mafia Block Deadman




Steel Sheet Piling with Single, Double, Continuous Beams
 

Jetting

The practice of jetting, applying a pressurized water jet at the toe of the pile, can greatly facilitate the driving of piles in some instances. The object of jetting is to loosen the soil, thereby reducing the resistance of the toe of the pile. The effectiveness of jetting depends upon the density of the soil and the availability of adequate water pressure.

Low-Pressure Jetting

This method is used in dense noncohesive soils in combination with a vibratory pile driver. Drivers with variable eccentricity are recommended when low-pressure jetting is used. Water pressure providing a pressure of 20 bar (0.42 lb/ft2) with a volume of 120 to 240 L (31.7 to 63.4 gal) per minute will be required; to be delivered through special nozzles.

High-Pressure Jetting

This method employs pressure of 250 to 500 bar (5.22 to 10.44 lb/ft2) and a water volume of 60 to 120 L/min (15.8 to 31.7 gal/min) also to be delivered through special nozzles.

Pile Driving Hammer Types

1. The drop hammer Rarely used, except for installing compacted-concrete piles.
2. Single-acting hammers Powered by steam or air pressure, which is used to raise the hammer ram for each down stroke. Gravity and the weight of the hammer deliver the kinetic energy required to drive the pile.
3. Double-acting hammers Generally powered by compressed air or hydraulics, which provides the power to raise the hammer ram and accelerate its fall.
4. Vibratory hammers Paired, oscillating rotating weights connected to the pile delivers anywhere from 0 to 2000 vibrations per minute at low frequency or from 0 to 8000 vibrations per minute for high-frequency hammers to drive the pile to design depth. This type hammer is effective only in granular or cohesiveless soils.

Diesel Pile Hammer Operation -A Five-Stage Cycle


Diesel pile hammers are operating as follows:

1. Raising of piston
For starting the Diesel pile hammer, the ram weight (piston) is raised by means of a tripping device and automatically released at a given height.

2. Injection of Diesel fuel and compression
While dropping, the piston will actuate the pump lever so that a given quantity of Diesel fuel is sprayed on top of impact block. After passing the exhaust ports, the piston will start compressing the air in the cylinder chamber.

3. Impact and explosion
The impact of the piston on the impact block will atomize the Diesel fuel in the combustion chamber. The atomized fuel will ignite in the highly compressed air. The resulting explosive energy will force up the piston.

4. Exhaust
While moving upwards, the piston will expose the exhaust ports.
Exhaust gases will escape and the pressure in the cylinder will equalize.

5. Scavenging
The piston keeps jumping upwards and will draw fresh air through the exhaust ports for scavenging the cylinder, while also releasing the pump lever. The pump lever returns to it’s starting position, so that the pump will again be charged with fuel.

Double-Acting Hydraulic Hammer-Type Pile Driver

The ram in a hydraulic hammer is lifted by hydraulic pressure, and on the downward stroke, additional energy is added to the ram. Pressurized nitrogen pushes the ram down.

Vibratory Pile Drivers

These types of pile drivers use vibration to penetrate the soil strata, using the theory of vibration to reduce the friction between the pile and the soil. These vibrations create soil liquefaction to some degree, causing soil particles to “float” and provide a significant decrease in resistance between the soil and the pile. The pile can be driven into the ground with very little added weight or pressure.
This vibratory head generates oscillations inside a vibration case where eccentric weights are geardriven by one or more motors. The crane from which the vibratory driver is attached must be isolated from the vibration case by rubber or spring cushions. The vibratory pile driver is frequently used to extract previously driven piles since the upward pull is substantially reduced. Vibratory pile drivers work best in noncohesive soils such as gravel and sand. These types of pile drivers also work quite well in water-saturated soils.

Minipiles and Micropiles

Micropiles are small diameter drilled and grouted friction piles. Each pile includes steel elements that are bonded into the bearing soil or rock - usually with cement grout. The bearing stratum is logged during installation drilling to assure that bearing capacity is adequate. Micropiles do not rely on end-bearing capacity, so there is no need to establish the competency of rock beyond bond-depth. They can be installed quickly in virtually every type of ground using highly adaptable mobile drilling equipment. These steel piles have working capacities up to 250 tons.
Rembco uses micropiles (minipiles) as an economical alternative to large diameter drilled
shaft foundations, especially in difficult ground conditions, karst geology, or restricted access situations.

Micropiles - Minipiles Setup Sequence:
Drilled into bedrock, micropiles or minipiles bond to the rock socket wall for load transfer.
  • The casings of the minipiles are advanced as piles are drilled into site's bedrock.
  • Drill pipe is removed, which leaves casing for mini or micro piles setting in bedrock.
  • A reinforcement load bar is lowered into casings of the micro piles, for added capacity.
  • Cementitious grout is pumped or pressure feed into the minipiles casings, bottom up.
  • The casings for the micro piles are lifted to top of bedrock, allows bonding to the bar.
  • Excess steel is cut from the tops of micropiles; piles are capped to engineer's design.
  • A select number of piles are load tested to prove the engineering load design.

Handling, Storage of Timber, Precast, Steel, and Concrete Piles

Unloading. Timber piles may be unloaded by controlled roll-off. Dumping should not be permitted.

Handling. Generally treated timber piles should not be handled with timber tongs, cant hooks, peaveys, or pile chains. Piles should be handled so as to avoid puncturing or breaking through their outer treated portion. AWPA standard M4-80 permits the use of pointed tools provided that the side surfaces of the pile are not penetrated more than 1/2 in (12.7 mm). This may be difficult to control.
Treated timber piles should not be dragged along the ground.

Storage. Timber piles in storage for any length of time should be on adequate blocking and supported to avoid permanent bends. Piles should be stacked on treated or nondecaying material and with an air space beneath them. Storage areas should be free of debris, decayed wood, and dry vegetation (this presents a fire hazard) and should have sufficient drainage to prevent the piles from lying in water.

Precast Piles

Unloading. Precast piles should be unloaded by lifting them in a horizontal position. Dumping or rolling off the precast piles should not be permitted.

Handling. Precast piles should be handled with proper slings attached to designated pickup points or inserts. Impact loads should be avoided.

Storage. If precast piles are stored on blocking, it should be placed at designated support points to avoid overstressing and cracking the piles.

Steel Pipe and Tube Piles

Unloading. Controlled dumping or roll-off unloading of pipe or tube piles may be permitted.

Handling.  Sufficient pickup points should be used to avoid bends in pipe or tube piles. A closed-end pile should not be dragged along the ground with the open end first.

Steel H Piles

Unloading. H piles should be unloaded by lifting them in a horizontal position. Dumping piles should be prohibited.

Handling. H piles lifted in a horizontal position should have their webs vertical to avoid bending.
Coated H piles must be carefully handled so as to avoid damage to the coating.


Storage. H piles should be stored on adequate blocking. Nesting of piles with their flanges vertical is recommended.

Pile Shells

Unloading. Dumping of pile shells should not be permitted, but they may be roll-off unloaded.

Handling. Pile shells should be handled at all times so as to avoid permanent deformations. A closed-end shell should not be dragged along the ground with the open end first.

Storage. Pile shells should be stored out of mud or standing water. If in storage for a long period of time, shells should be protected from the elements.

Handling Cement and Concrete for Pilings

Cement

Storage. Bag cement must be stored off the ground on adequate racks and protected from the elements, especially moisture.

Concrete Aggregates

Handling. Aggregates should be handled so as to avoid breakage, segregation, and contamination.
The required gradation must be maintained.

Storage. See Concrete Production Facilities: Storage Facilities under Pile Material.


Handling Reinforcement

Reinforcement

Handling. Reinforcing steel should be handled in bundles with appropriate lifting slings located at sufficient pickup points to avoid permanent bending. Bundles should not be broken until the steel is to be used. All necessary precautions must be taken to maintain the identification of the steel after the bundles have been broken. This can be done by keeping the steel separated according to type, size, and length with a tagged piece in each stack.

Storage. Reinforcing steel should be stored off the ground on suitable racks or blocking so as to avoid permanent bends. The steel should be stored so as to prevent excessive rusting and contamination by dirt, grease, or other bond-breaking coatings.

Typical Specifications for Cast-in-Place Concrete Piles - part 2

>>>    part1

Mixing Time. Mixing time starts when the water is added to the mix and should be adequate but not excessive. Minimum mixing times vary with the size and type of the mixer and range from 1 to 3 minutes. Maximum mixing times can range from 3 to 10 minutes. For stationary mixers, minimum mixing time can be established by tests on mixer performance. For truck-mixed concrete, complete mixing requires from 50 to 100 revolutions of the drum at mixing speed. Check the manufacturer’s plate on the mixer. If, after mixing, drum speed is reduced to agitation speed or stopped, the drum should be rotated at mixing speed for from 10 to 15 revolutions just before concrete is discharged.

Elapsed Time. For normal temperatures, the total time from start of mixing to discharge should not exceed about 11/2 hours and should be reduced as temperatures increase.The mix should be discharged before 300 revolutions of the drum.

Slump. Slump tests should be made periodically in accordance with ASTM C143, Standard
Method of Test for Slump of Portland Cement Concrete, to ensure that concrete has the specified slump for proper placement in pile casings, shells, or holes. The slump for concrete as delivered to the top of the pile casing or hole should be 5 in (127 mm) for conventional concrete or 4 in (101.6 mm) for reduced coarse aggregate concrete, both with a tolerance of +2 in, -1 in (+50.8 mm,-25.4 mm). Special-type piles may require concrete having different slumps. See Special-Type Piles.
Sometimes it is advisable to check the slump just before adding the final water at the jobsite to avoid too high a slump or a wet mix.

Slump Loss. Slump loss can be caused by overmixing, hot weather, pumping through long lines, or delays in delivery and placement of concrete. Overmixing can and should be avoided. If necessary, all the mix water can be added and all mixing done upon delivery at the jobsite. This could prevent overmixing and may help in eliminating slump loss due to hot weather. If concrete is to be pumped to the pile locations, the slump should be increased without changing the water-cement ratio or concrete strength to compensate for slump loss during pumping. All preparations should be made for depositing concrete upon delivery, and delivery schedules should be arranged to eliminate delays in placing concrete.

Retempering. The addition of water to the concrete mix to compensate for slump loss resulting from delays in delivery or placing is permissible provided the design water-cement ratio is not exceeded and the concrete has not attained its initial set. Initial set is not to be confused with a false set, when the concrete appears to stiffen but can be made workable with agitation.

Delivery Tickets. A delivery ticket must accompany each load or batch of concrete. The delivery ticket is for the purchaser, but the inspector should be furnished a copy. It should include sufficient data to identify the producer, project, contractor (purchaser), truck mixer used, and specified concrete mix or strength. Other information which should be on the delivery ticket is the date of delivery, type and brand of cement, maximum aggregate size, weights of cement, sand, and coarse aggregate, type and amount of admixtures, quantity of water, time batched, reading of revolution counter and time when water was first added, volume of batch, and amount of water added by the receiver. The inspector should note the times of delivery and placement and the air temperature.

Concrete Strength. Standard cylinders for compression tests should be made periodically or as specified in accordance with ASTM C31, Standard Method for Making and Curing Concrete Test Specimens in the Field, to ensure that concrete of required strength is being furnished. The frequency for making test cylinders will vary with the job size and other factors, but generally a test set (minimum of two cylinders) should be made for each daily pour or for every 50 yd^3(38.2 m3) placed.
Also a test set should be made for each age at which compression tests are to be run. The inspector should ensure that cylinders are properly cast, handled, stored, sealed, packaged for shipment, and shipped so as not to invalidate test results. For strict concrete control, test specimens should be cast in cast-iron or tin-can molds. Although widely used, cardboard or paper molds are not recommended for molding test cylinders for strict concrete control. If cardboard molds are used, they should conform with ASTM C470, Specifications for Molds for Forming Concrete Test Cylinders Vertically. Jobsite curing or the use of cardboard molds may contribute to low strength-test results. Grout strengths for special-type piles are determined by standard cube tests in accordance with ASTM C91, Specification for Masonry Cement. (See Auger-Grout Pile, Cast-in-Place Pile, and Minipiles under Special type Piles.)

Results of Tests. The pile inspector should be furnished with copies of the results of all concrete compression tests as called for in the specifications. It is advisable to obtain 3- and 7-day results at the beginning of the job in order to detect trends in concrete strengths. The results of 7-day tests are also valuable in monitoring concrete strength trends as the job progresses so that, if necessary, remedial measures can be taken before too much concrete is placed.

Strength Variations. Variations in concrete strength as determined by standard cylinder tests are normal. Several criteria are used to determine the acceptability of variations. For example, the concrete is considered satisfactory if the average of three consecutive tests is equal to or greater than the required 28-day strength and no test falls below the required 28-day strength by more than 500 psi (3447 kPa). Another acceptance criterion is that 80 percent of the tests show strengths greater than the design strength and that not more than 1 test in 10 is less than the required 28-day strength. A third is that the average strength from consecutive tests is greater than the required 28-day strength. ACI 214.3-88 provides recommendations on evaluating concrete strength-test results.
If the test results show that concrete strength is below that specified, the cause of low-strength concrete should be investigated. Low strength could be caused by unsatisfactory materials, by improper batching and mixing, or by the use of excess water in the mix. Low cylinder breaks could also result from improperly preparing, curing, handling, or testing cylinder specimens.

Verification of Concrete Strengths. If the results of standard cylinder tests are low, cores can be removed from piles for testing. Core tests are considered satisfactory if the average of three cores is equal to or greater than 85 percent of the required 28-day strength and if no core strength is less than 75 percent of the specified 28-day strength. The results of tests on cores are normally lower than those on standard cylinders owing to microfracturing of the concrete. It should be noted that pile concrete in a long steel shell embedded in the ground will cure at a rate slower than that for test cylinders or exposed concrete. Curing conditions are ideal, but the rate of strength gain is lower than normal. Concrete strength in completed piles can also be checked by various nondestructive methods such as penetration-resistance tests. See ASTM C803, Method of Tests for Penetration Resistance of Hardened Concrete.

Typical Specifications for Cast-in-Place Concrete Piles - part 1

Design Mix. A design mix with results of tests on standard cylinders should be furnished by the contractor. Copies of these data should be made available to the inspector at the start of pile installation.

Concrete Production Facilities. Concrete may be mixed in portable mixers brought to the pile locations, but generally it will be ready-mixed. Ready-mix concrete may be (1) batched and mixed at a central plant and delivered to the pile locations in agitating or in agitating trucks (central-mixed), (2) batched at a central plant and mixed in a truck mixer in transit to or after reaching the jobsite (truck-mixed), or (3) partially centrally mixed with mixing completed in a truck mixer in route to the job or on the jobsite (shrink-mixed). The central plant may be located on the jobsite.
The concrete batch and mixing plant should be inspected for adequacy of storage facilities for materials, accuracy, and reliability of batching equipment, condition of mixing equipment, and proper operational procedures.

Storage Facilities. Cement must be kept dry whether it is stored in bulk containers or in bags.

To avoid contamination, stockpiles of aggregates that have been cleaned, graded, and prepared for batching should be on a hard, clean base with the area around the stockpiles spread with a bedding material of sand, gravel, or rock. Side slopes of stockpiles should not exceed 7 in/ft (583 mm or less per meter) to prevent segregation. Coarse aggregate should be separated by type and size gradation.
Overlapping of stockpiles should be prevented and suitable drainage should be provided.
All reasonable precautions should be taken to keep the moisture content of aggregates as nearly uniform as possible.

Batching Equipment. Concrete is usually batched by weight. Batching scales should have recent calibration and certificate of inspection and must be clean and free of interference by other objects. Separate weight-batching facilities should be provided for cement. Batch-weight recording and cutoff devices must operate accurately. The bottom of batch bins must be fully sloped in all directions. Water-metering devices, whether at a central mixing plant or mounted on a truck mixer, must be accurate and equipped with indicating dials and totalizers.

Mixing Equipment. All mixing equipment, whether stationary or truck-mounted, must be in
good operating condition. The interior of drums should be clean, and mixing blades should not show signs of wear in excess of 1 in (25.4 mm). Truck mixers must be equipped with a reliable revolution counter.

Operations. All materials must be accurately batched, and batching should be by weight. Admixtures, if required, must also be accurately measured. Mixing drums must be cleaned after each use to prevent an accumulation of hardened concrete on the blades. All washwater must be removed from the mixing drum prior to batching. Cement should be used on the basis of first in-first out. The free-water content of the aggregates should be included as part of the total mix water. Aggregates should be allowed sufficient time to drain, and it may be necessary to have a moisture meter in the sand batcher to monitor moisture content. Proper equipment and methods must be used for handling aggregates to avoid segregation and breakage. Segregation of coarse aggregate can be reduced by separating it into several size fractions and batching them separately. Finished screening of aggregates at the batcher is recommended to avoid problems of segregation and contamination.

Concrete Materials. Materials including cement, sand, coarse aggregate, and water should be inspected for compliance with specifications and accepted practice.

Cement. Cement must be of the type specified or permitted with the approval of the engineer.
Mill certificates should be furnished to show that cement conforms with the requirements of the specifications and ASTM C150, Standard Specifications for Portland Cement.Type IV cement should not be used for pile concrete. Type III, or high-early, cement may be permitted for cast-in-place concrete test piles to get a fast gain in strength. Type II or Type V cement may be specified for sulfate exposure.
Cement remaining in bulk storage for more than 6 months or cement stored in bags longer than
3months should be retested before use to ensure that it meets the requirements of ASTM C150.
Cement should not be used directly from the mill if it is still hot. The cement should be allowed to cool before using to reduce the possible occurrence of false sets.
Cement should be inspected for lumps caused by moisture. Cement bags should be inspected for rips, punctures, or other defects. If cement is to be batched by bag, the weights of bags should be spot-checked and should not vary by more than 3 percent.

Sand. Sand should be clean, sharp, well graded, and free of silt, clay, or organic material. The specific gravity and/or fineness modulus may be specified for special mixes such as reduced coarse aggregate concrete.

Coarse Aggregate. Specifications may permit gravel or crushed stone. The use of crushed rock aggregate requires more cement and sand for comparable workability. Air entrainment also improves workability. Lightweight aggregates are not recommended, and slag aggregates are not generally used. Alkali-reactive aggregates or aggregates from shales, friable sandstone, chert, and clayey or micaceous rock should not be permitted. Aggregates should be uncoated and free of silt, clay, organic material, and chemical salts. The specific gravity of the coarse aggregate may be specified. Aggregates should be well graded with a maximum size of  ¾  in (19.05 mm) and with the amounts of aggregates less than
3/16 in (4.762 mm undersize) held uniform and within 3 percent.

Water. As a general rule, mix water should be potable. It should contain no impurities which would affect the quality of the concrete. It should not have a sweet, saline, or brackish taste or contain silt or suspended solids. Very hard water may contain high concentrations of sulfate. Well water from arid regions may contain harmful dissolved mineral salts. If questionable, the water can be chemically analyzed.The quality of the water can be checked by comparing the strength of concrete reached at various ages for a mix using the water of unknown quality with the results of similar age tests on a mix made with water which is known to be acceptable. Impurities in mix water may affect both the compressive strength of the concrete and its setting time.

Admixtures. The authorized or mandatory use of admixtures will be noted on the mix design report. Special admixtures such as retarders and fluidizers may be required for pumped concrete.

Cold-Weather Operations. The minimum temperature of fresh concrete as mixed should be about 45°F (7.2°C) for air temperatures above 30°F (-1.1°C), 50°F (10°C) for air temperatures from 0 to 30°F ([1]17.2 to -1.1°C), and 55°F (12.7°C) for air temperatures below 0°F (-17.2°C). Frozen aggregate or aggregates containing lumps of ice should be thawed before being used. It may be necessary to preheat the mix water and/or the aggregate. For air temperatures between 30 and 40°F (-1.1 and 7.2°C), it is usually necessary only to heat the water to a maximum of about 140°F (60°C).
For air temperatures below 30°F (-1.1°C), the water can be heated to 140 to 212°F (60 to 100°C) and the aggregate to about 45 to 55°F (7.2 to 12.7°C). Overheating should be avoided. If both the mix water and the aggregates are preheated, it is recommended that the water be mixed with the aggregates before adding the cement to avoid a flash set. The temperature of the water-aggregate mixture should not be higher than 80°F (26.6°C) and preferably about 60°F (15.5°C).

Hot-Weather Operations. If the temperature of the concrete during mixing is above 80°F
(26.6°C), it could result in increased water demand (slump loss) or an accelerated set. The easiest way to control and reduce the concrete temperature is by using cold mix water, which can be achieved by mechanical refrigeration or by using crushed ice as part or all of the mix water. Mixing time should be kept to a minimum, and mixing drums, water tanks, and pipe should be painted white.

>>>   part 2

 

Steel Pipe Piles and Conical Points

 
CONICAL POINTS FOR PIPE PILES

 

Copyright@2010 INGENIERÍA ECONÓMICA